Five Fields Phase III

August 29, 2016

Due to rain over weekend contractor had additional grading and utility work to complete that took longer than expected therefore, paving re-scheduled to start tomorrow 8-30-16.

----------------------------------------------------------------------------------------------------------------------------------------------------------------------
 
August 25, 2016

Due to recent rain the contractor has been delayed.  The updated schedule is to continue with grading and undercutting tomorrow and Saturday.  Paving is scheduled to start on Monday 8-29-16. The  utility contractor will be on site today and tomorrow to complete their work.  The above is dependent on weather conditions.

-----------------------------------------------------------------------------------------------------------------------------------------------------------------------


August 19,2016

The contractor will not be working tomorrow Saturday 8-20-2016 due to rain.  They will resume work on Monday 8-22-2016.

----------------------------------------------------------------------------------------------------------------------------------------------------------------------

August 15, 2016

Contractor will begin grading and undercutting (removing "soft areas") in road tomorrow. Contractor may drop off grading equipment later today. Access to driveways will be limited during working hours but will be ramped at end of work day.  Contractor and/or Ruekert-Mielke inspector will contact you prior to limiting access to your driveway.  Additional utility work and restoration is scheduled for later this week and paving scheduled for next week.  If you have any questions or concerns you can contact Maggie Wagner or Marianne Hiltunen from the City of Pewaukee at (262)691-0804.

------------------------------------------------------------------------------------------------------------------------------------------------------------------------

August 9,2016

Concrete work should be completed by Wednesday August 10, 2016 and milling operations will start on Saturday August 13th at 8:00 am.  Contractor plans to have all areas milled on Saturday and will start grading roads on Monday August 15th. If you have any questions you can contact our on site inspector Brett Glaeser from Ruekert-Mielke at (920)323-9724.  You may also contact Maggie Wagner or Marianne Hiltunen from the City of Pewaukee at (262) 691-0804 with any construction concerns.

------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 

August 3, 2016

Tomorrow and Friday DC Burbach (concrete contractor) will be on site to remove curb and gutter.  They will contact any home owners with repairs in their driveways.  Concrete placement should occur with in a couple days of removals.  If you have any questions or concerns you can contact Maggie Wagner or Marianne Hiltunen from the City of Pewaukee at 262-691-0804.

-------------------------------------------------------------------------------------------------------------------------------------------------------------------


August 3,2016

Saw cutting of concrete has been completed.  Concrete contractor (DC Burbach) and/or Ruekert-Mielke inspector will be contacting residents with repairs in the driveways prior to any removals.  Pavement milling has been postponed until August 12, 2016. 


July 27, 2016

The City's onsite inspector for the project is Brett Glaeser from Ruekert Mielke.  If you have a concern about the construction underway, you can contact him at 920-323-9724.  You may also contact Maggie Wagner or Marianne Hiltunen from the City of Pewaukee at 262-691-0804 with any construction related concerns.

---------------------------------------------------------------------------------------------------------------------

July 13, 2016

The project was awarded to Payne & Dolan, Inc., who will be the general contractor for the project.  The Contractor tentatively plans to begin work on the project starting the week of July 25, 2016.  The initial stages of this work will consist of replacing various sections of curb within the project limits.  This work will last approximately 1 to 1 ½ weeks depending on weather conditions.  The pavement will remain intact for the duration of this work, however there will be equipment staged in the areas of curb replacement which may impede traffic.  Additionally, some sections of curb will be replaced within driveways.  This will limit driveway access for up to 3 days while the concrete is curing (i.e. hardening).  We will work directly with the affected property owner(s) in terms of notifications and alternate accesses for this work.

 Pavement milling operations (removal of the existing asphalt) are currently scheduled for the week of August 8, 2016.  Once the pavement is removed, access to your driveways will be maintained on the gravel base.  Milling operations will be followed by undercuts (digging out bad or soft stone base areas and replacing them with appropriate backfill to support the new pavement) and grading to re-establish the crown (pitch) on the roadway.  These operations will take 1 to 1 ½ weeks depending on weather conditions and the amount of undercutting that is required to be completed.  

 The new asphalt will be placed in 2 layers.  The binder (lower) asphalt course is currently scheduled to begin the week of August 15, 2016.  The surface (finish) asphalt course will follow immediately upon completion of the binder course.  During this time, access to your driveways may be limited for short periods (perhaps 30 minutes to 1 hour) while the asphalt is placed, rolled and cooled.  The time to cool the asphalt is weather dependent so the time your access is limited can vary.  The contractor and our resident project representative will do their best to provide access to your property as soon as possible.

 We will have our resident project representative on site full time during this project and will post their contact information as soon as it becomes known.

As with any construction project, this schedule is subject to change due to weather conditions or subsurface conditions that are discovered in the construction process.  We appreciate your patience during this construction project.  If you should have any questions or concerns regarding this project, please feel free to contact Maggie Wagner or Marianne Hiltunen at 262-691-0804.

----------------------------------------------------------------------------------------------------------

June 27, 2016
The Five Fields Phase III road project was awarded at the June 6th public hearing.  Construction is estimated to begin in July.  Once a firm date has been set for the start date by the contractor, the affected residents will be notified by mail.

If you have any questions regarding this project, please contact Engineering at 262-691-0804.

----------------------------------------------------------------------------------------------------------


The road projects will consist of spot repair of curb and gutter, spot inlet repairs, full depth mill of existing pavement (removing all the existing asphalt pavement), spot repairs to the base (stone) and subgrade, and placing 5” of new asphalt.  Phase III project encompasses the following locations:

Greenfield Court (all)
Greenfield Lane (all)
Littlefield Blvd (all)
Rough Hill Road from Littlefield Blvd to Fieldside Rd
Fieldside Road from Rough Hill Road to Greenbriar Road

The Public Hearing for the project and its assessments is scheduled for June 6th 2016 at 7:00 pm at the City Hall Common Council Chambers.  Notices were mailed to affected residents on May 19, 2016.

If you have questions regarding this project, please contact Engineering at 262-691-0804.