Bluemound East Industrial Park

September 28, 2016

Surface paving is scheduled to continue this evening weather permitting.  If you have any questions or concerns you can contact Maggie Wagner or Marianne Hiltunen from the City of Pewaukee at (262)691-0804.

------------------------------------------------------------------------------------------------------------------------------------------------------------------------

September 26, 2016

Surface paving is scheduled for tonight (9-26-16) and Tuesday (9-27-16) night.  If you have any questions or concerns you can contact Maggie Wagner or Marianne Hiltunen from the City of Pewaukee at (262)691-0804

----------------------------------------------------------------------------------------------------------------------------------------------------------------------

September 21, 2016

Due to rain Payne & Dolan has delayed surface paving until Friday (9-23-2016) and Saturday (9-24-2016) nights depending on weather conditions.  Their alternate nights for paving are Saturday (9-24-2016) and Sunday (9-25-2016) weather permitting.  If you have any questions or concerns you can contact Maggie Wagner or Marianne Hiltunen from the City of Pewaukee at (262) 691-0804.

----------------------------------------------------------------------------------------------------------------------------------------------------------------------



September 16, 2016

Payne and Dolan will be paving the binder and surface courses of pavement at night.  They plan to start this Sunday night (9-18-2016).  Their working hours will be from 7:00 PM to 7:00 AM.  Weather permitting they should have the paving completed by Thursday morning (9-22-2016).The road and utility work will continue thru this Saturday (9-17-2016) in anticipation to start paving Sunday night.  If you have any questions or concerns you can contact Maggie Wagner or Marianne Hiltunen from the City of Pewaukee at (262) 691-0804.  Tom Williamson our on site inspector with Ruekert-Mielke can also be contacted at (262) 239-8309.

---------------------------------------------------------------------------------------------------------------------------------------------------------------------


August 29,2016

Concrete contractor is scheduled to start placing concrete tomorrow 8-30-16.  Milling of road will be week of Sept 5, 2016  with grading to follow the week of Sept 12, 2016 and paving the week of Sept 19,2016.  The above is dependent on weather conditions and amount of undercutting needed to stabilize road base.  If you have any questions or concerns you can contact Maggie Wagner or Marianne Hiltunen from the City of Pewaukee at (262)691-0804. Tom Williamson our on site inspector with Ruekert-Mielke can also be contacted at (262)239-8309.

-----------------------------------------------------------------------------------------------------------------------------------------------------------------

August 15,2016

Concrete contractor is scheduled to begin saw cutting curb and gutter on Wednesday 8-17-16.  Removal and concrete replacement will continue into the next week.  The contractor and/or Ruekert-Mielke inspector will contact any business owners with concrete work being done in the drive approach to schedule best removal and replacement times.  Milling is scheduled for week of September 5th, 2016.  If you have any questions or concerns you can contact Maggie Wagner or Marianne Hiltunen form the City of Pewaukee at (262)691-0804.

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------

August 9,2016

Construction work on culvert repairs will resume on Wednesday August 10, 2016.  Concrete work is scheduled to start next week.  If you have any questions you can contact our on site inspector Tom Williamson with Ruekert-Mielke at (262)239-8309. You may also contact Maggie Wagner or Marianne Hiltunen with the City of Pewaukee at (262)691-0804 for any construction concerns.


July 27, 2016

The project was awarded to Payne & Dolan, Inc., who will be the general contractor for the project.  The Contractor tentatively plans to begin work on the project starting the week of August 1, 2016.  The initial stages of this work will consist of replacing various sections of curb, inlet and utility repairs, and ditching and culvert work within the project limits.  This work will last approximately 3 weeks depending on weather conditions.  The pavement will remain intact for the duration of this work, however there will be equipment staged in the areas of this work which may impede traffic.  Additionally, some sections of curb will be replaced within driveways.  This will limit driveway access for up to 3 days while the concrete is curing (i.e. hardening).  We will work directly with the affected property owner(s) in terms of notifications and alternate accesses during this work.

Pavement milling operations (removal of the existing asphalt) are currently scheduled for the week of August 22, 2016.  Once the pavement is removed, access to your driveways will be maintained on the gravel base.  Milling operations will be followed by undercuts (digging out bad or soft stone base areas and replacing them with appropriate backfill to support the new pavement) and grading to re-establish the crown (pitch) on the roadway.  These operations will take 2 to 2 ½ weeks depending on weather conditions and the amount of undercutting that is required to be completed.  

The new asphalt will be placed in 2 layers.  The binder (lower) asphalt course is currently scheduled to begin the week of September 5, 2016.  The surface (finish) asphalt course will follow immediately upon completion of the binder course.  During this time, access to your driveways may be limited for short periods (perhaps 30 minutes to 1 hour) while the asphalt is placed, rolled and cooled.  The time to cool the asphalt is weather dependent so the time your access is limited can vary.  The contractor and our resident project representative will do their best to provide access to your property as soon as possible.

We will have our resident project representative on site full time during this project and will post their contact information as soon as it becomes known.

As with any construction project, this schedule is subject to change due to weather conditions or subsurface conditions that are discovered in the construction process.  We appreciate your patience during this construction project.  If you should have any questions or concerns regarding this project, please feel free to contact Maggie Wagner or Marianne Hiltunen at 262-691-0804.

------------------------------------------------------------------------------------------------------------

July 13, 2016

The Bluemound East Industrial Park project was awarded to Payne & Dolan on June 27, 2016.  Details on construction start date will be coming soon.

If you have questions regarding this project, please contact Engineering at 262-691-0804.


---------------------------------------------------------------------------------------------------------------

The road projects will consist of spot repair of curb and gutter, spot inlet repairs, culvert cleaning and ditch restoration, full depth mill of existing pavement (removing all the existing asphalt pavement), spot repairs to the base (stone) and subgrade, and placing 6” of new asphalt.  Bluemound East Industrial Park project encompasses the following locations:

Saratoga Road (all)
Johnson Road (all)
Cheaney Road(all)

The Public Hearing for the project and its assessments is scheduled for June 27th 2016 at 7 PM at the City Hall Common Council Chambers.  Notices have been mailed to the affected properties.

If you have questions regarding this project, please contact Engineering at 262-691-0804.