Five Fields Phase IV
Five Fields Phase IV
Hunters Ridge, Greenbriar Court, Greenbriar Road, Stonewall Court, and Ridgecrest Court

Schedule coming soon....

Schedule as of August 3, 2017

We have determined the contractor may be starting construction as early as August 4, 2017 with saw cutting.  The beginning stages of this work will seem intermittent as minor utility work is being completed and curb sections are being replaced.  This work will last approximately 1 to 2 weeks depending on weather conditions.  The road pavement will remain intact for the duration of this work, but there will be equipment and barricades/barrels in the areas of curb replacement and utility work which will impede traffic.  Some driveway access may be limited for up to 3 days while the concrete is curing.  If this is the case, we will work directly with the property owner with notification and alternate accesses.

 The roadways will have a full depth mill (all existing asphalt removed).  The pavement milling is currently scheduled the week of August 18, 2017.  Once the pavement is removed, access will be maintained to your driveways on the gravel base.  Milling operations will be followed by undercuts (digging out bad, soft stone base areas and replacing them with appropriate backfill to support the new pavement).  This is then followed by grading operations to re-establish the crown (pitch) on the roadway.  These operations will take 1 to 2 weeks depending on weather conditions and the amount of undercuts. 

 The new asphalt will be placed in 2 layers.  The binder (lower) asphalt course is currently scheduled to begin the week of August 23, 2017.  The surface (finish) asphalt course will follow immediately upon completion of the binder course for all areas.  During this time, access to your driveways may be limited for short periods (perhaps 30 minutes to 1 hour) while the asphalt is placed and cooled.  The time to cool the asphalt is weather dependent so your access limit time may vary.  The contractor and our inspector will do their best to get access to your properties as soon as possible.

 We will have full time inspection on this project.  The onsite inspector will be Rich Eberhardt, Ruekert Mielke.  He may be reached at 414-659-6145 for construction related questions.  You may also contact the City at 262-691-0804 with any questions or concerns.


Sprinklers & Dog Fence in right of way
If you have any invisible fencing or an irrigation system (or any other impediments underground) located within the City’s right of way (typically from the curb towards your home approximately 16’), you must mark the locations of the these facilities.  If you do not mark the location and it is damaged by the Contractor, it will be your responsibility to repair the damage.  If it is marked and damaged by the Contractor, the Contractor will be responsible for the repair.