Meadowbrook Farms Phase 1 road project includes road rehabilitation on Deer Haven Court, Shooting Star Court, and Shooting Star Road from Shooting Star Boulevard to Deer Haven Drive.  The existing pavement will be removed and replaced.  Minor storm sewer, sanitary sewer and water main work will be completed as part of the project as well.  Construction is anticipated to begin the week of July 12, 2021.

Assessment Notices

Meadowbrook Farms Assessment Letter

Meadowbrook Farms Phase 1 Preliminary Engineers Report


August 13, 2021

We understand that garbage collection has been delayed this week.  It is scheduled to be picked up today, August 13.  Additionally, an updated project schedule is posted below.

Project Schedule

Scheduled Date
Description of Work
08/13
Finish milling off the old asphalt
08/16
Replacing old storm sewers along Shooting Star Road
08/16-20
Repairing storm sewer structures along Shooting Star Court and Shooting Star Road
08/23
Paving binder (first lift of asphalt) course on all roads
08/24
Paving surface (second lift of asphalt) course on all roads
08/25
Removing any debris from storm sewers and lining them to increase lifespan