July 6, 2021
Meadowbrook Farms Phase 1 road project includes road rehabilitation on Deer Haven Court, Shooting Star Court, and Shooting Star Road from Shooting Star Boulevard to Deer Haven Drive. The existing pavement will be removed and replaced. Minor storm sewer, sanitary sewer and water main work will be completed as part of the project as well. Construction is anticipated to begin the week of July 12, 2021.
Assessment Notices
Meadowbrook Farms Assessment Letter
Meadowbrook Farms Phase 1 Preliminary Engineers Report
August 13, 2021
We understand that garbage collection has been delayed this week. It is scheduled to be picked up today, August 13. Additionally, an updated project schedule is posted below.
Project Schedule
Scheduled Date
| Description of Work
|
---|
08/13
| Finish milling off the old asphalt
|
08/16
| Replacing old storm sewers along Shooting Star Road
|
08/16-20
| Repairing storm sewer structures along Shooting Star Court and Shooting Star Road
|
08/23
| Paving binder (first lift of asphalt) course on all roads
|
08/24
| Paving surface (second lift of asphalt) course on all roads
|
08/25
| Removing any debris from storm sewers and lining them to increase lifespan
|